Hi BJ,
the thing is that WIP never ever goes to the inventory wheather the whole
process is completed or just its corresponding completion task got completed.
My query is that I have to generate the intermediate product so that if my
successive task is not able to run by some way due to some disturbances in my
facility(in real time) then it should get stored as an inventory for the future
use. How can i achieve it ?
Thanks
Brijesh M.
BJ Freeman <[EMAIL PROTECTED]> wrote: By final step I mean all steps completed
and you have the finished product.
BJ Freeman sent the following on 7/27/2008 10:18 AM:
> Though Jacopo gave you the technical answer
> I think of it this way:
> WIP as a parts on a cart or conveyor belt that got though processes
> before they are finished. so they don't go to inventory, until the final
> step.
>
> brijesh m sent the following on 7/27/2008 5:00 AM:
>> Hi friends,
>> I have given the status of "work in progress"(WIP) to the product in the
>> intermediate stage of my manufacturing process. But after completion of its
>> corresponding producing task this product(WIP) was not incremented in
>> inventory. Is there any way out ?
>>
>>
>> Thanks
>> Brijesh M.
>>
>>
>
>
>
>