Hello All,

Is there any process to create subtask in Project Mgr.
I have done the following steps:

1) I have  create a Project.
2) Create the  Phases for Project.
3) Create the tasks for related Phase.

For creating the task we pass the Phase workEffortId as workEffortParentId for the task. Now I want to create the subtask for already created task, But in Project Mgr component i am not able to find the way to create the subtask.

Thanks
-----------
Deepak Dixit

Reply via email to