Do you mean that we can not create any sub task of a task directly.
For creating subtask we need to add subproject.

Thanks
---------
Deepak Dixit


Hans Bakker wrote:
you can see phases as task groups under which the actual tasks are.

the maximum is 3 levels, however project can consist out of sub projects
so the tree will be unlimited......

Regards,
Hans

On Thu, 2009-05-14 at 17:31 +0530, Deepak Dixit wrote:
Hello All,

Is there any process to create subtask in Project Mgr.
I have done the following steps:

1) I have  create a Project.
2) Create the  Phases for Project.
3) Create the tasks for related Phase.

For creating the task we pass the Phase workEffortId as workEffortParentId for the task. Now I want to create the subtask for already created task, But in Project Mgr component i am not able to find the way to create the subtask.

Thanks
-----------
Deepak Dixit

Reply via email to