Do you mean that we can not create any sub task of a task directly.
For creating subtask we need to add subproject.
Thanks
---------
Deepak Dixit
Hans Bakker wrote:
you can see phases as task groups under which the actual tasks are.
the maximum is 3 levels, however project can consist out of sub projects
so the tree will be unlimited......
Regards,
Hans
On Thu, 2009-05-14 at 17:31 +0530, Deepak Dixit wrote:
Hello All,
Is there any process to create subtask in Project Mgr.
I have done the following steps:
1) I have create a Project.
2) Create the Phases for Project.
3) Create the tasks for related Phase.
For creating the task we pass the Phase workEffortId as
workEffortParentId for the task.
Now I want to create the subtask for already created task, But in
Project Mgr component i am not able to find the way to create the subtask.
Thanks
-----------
Deepak Dixit