On Fri, May 14, 2021 at 5:13 PM jerome moliere <jer...@javaxpert.com> wrote:
>
> Hi all,
> I would like to know the best practices to migrate a mission critical Solr
> cluster from version 6.x to 8.x without any service shutdown.
> Is the double upgrade required (mandatory) ?
> We can introduce another temporary group of machines ro join the cluster,
> then we may stop the existing nodes one by one once upgrade done...
> In this case we have  different indexes  and 2 replicas per shard...
>
> Is it possible to have concurently 2 versions of SolR running in the same
> cluster?
> Of course a full reindexing seems to be required , there is no problem we
> have enough time ( upgrade procedure is not required to be finished in a
> short time).
> I would like to have a summary of options available , pros & cons for each
> one and if possible a few tips & tricks to avoid some pitfalls...
>
> If you have good pointers to share and any feedback from production
> upgrades they will be welcome...
> Thanks for your help .
> Kind regards

With the (lack of) constraints mentioned here I think the easiest path
is a new cluster, full re-index, and then swap over your clients.

Reply via email to