-----BEGIN PGP SIGNED MESSAGE----- Hash: SHA1 Hi everybody! Since Espreon already asked me for my plans and I don't know the amount of time I'll have in the next week I'd like to start planning for 1.10.1 right now. It seems as if there are only rather smaller bugs in 1.10.0, so no critical bugfix release is/was required so far. Some bugfixes were done over time anyway and at least one new strings (for the Ukrainian translation) was added, so I got to run a pot-update and give the translators 1 week time to fix up stuff. In case you got any smaller string changes left for 1.10.1 (to fix mistakes or stuff which is simply wrong!) please make sure to commit them until 18.02.2012, 13:00 UTC+1 (that is the timezone currently active in Germany). This way I can run the pot-update right afterwards, inform the translators and, the most important part, tag the release on Saturday, 25.02.2012.
Short version: * commit string changes till Saturday, 18.02.2012, 13:00 UTC+1 * hard string freeze on branches/1.10 from 18.02.2012, 13:00 UTC+1 till the tagging of 1.10.1 * tagging of 1.10.1 planned for Saturday, 25.02.2012 Is there anything speaking against this plan? Cheers, Nils Kneuper aka Ivanovic -----BEGIN PGP SIGNATURE----- Version: GnuPG v2.0.18 (GNU/Linux) iEYEARECAAYFAk8+L6YACgkQfFda9thizwV7SQCfcTlGxLe7SWiVL9MrohRS/j85 JZoAoJo13Iw4vxCKAsPzh//sQk/FmeEj =skCT -----END PGP SIGNATURE----- _______________________________________________ Wesnoth-dev mailing list [email protected] https://mail.gna.org/listinfo/wesnoth-dev