I'm good as far as AI work is concerned. The Son of the Black Eye rebalancing won't be done by Dec 21 (neither of us has had much time for this lately), but we'll have the strings and significant changes to the scenarios done by then. After that, it's only straight rebalancing, no adding of new features or anything, so as long as we can do that after the string/feature freeze, we're good with that too.
On 12/11/13 4:28 PM, Ignacio Riquelme Morelle wrote:> On Sunday 10 November 2013 10:31:20 Nils Kneuper wrote: >> The more important question though is when to work on the next stable >> series. The last stable series is now getting close to 2 years old. He >> mentioned that having 1.11.8 as start of a feature freeze would make sense >> to him. My question to you folks is if this will also work for you. This is >> what I would propose as timeline for the 1.12 series: >> >> * Start of feature (and string!) freeze with 1.11.8 shortly before Christmas >> (December 21st?) >> * Stabilization phase for ~2 month (with a release every ~3 weeks) >> * Start of RC time mid February (hopefully only 1 RC), might be a possible >> time for branching off the new stable branch >> * Release of 1.12.0 around March 1st 2014 >> >> What do you think of a plan like this? Will this work for you? > > There has been pretty much no relevant activity in this thread since it was > started other than lipk and fabi's posts, but given those and their commit > activity since then, my impression is that a feature freeze on 1.11.8 is > considered to not be feasible? > > What's the situation for the other active committers? >
_______________________________________________ Wesnoth-dev mailing list [email protected] https://mail.gna.org/listinfo/wesnoth-dev
