Íñigo Goiri commented on YARN-999:
----------------------------------
For completeness, I did a full test end to end on Azure.
I created a cluster with 2 RMs in HA (using the capacity scheduler) and 1 NM
with 6GB of memory running the current trunk (which includes the REST API from
YARN-996).
Then I did the following:
# Started a long TeraGen job with 1 AM (2GB) and 2 Mappers (1GB each).
# Used the REST API to decreased the memory to 3GB. This triggered a reduction
in resources and showed -1GB available. It never killed any container.
# Replaced the RM jars with the code in [^YARN-999.007.patch] and made it
active.
# Decreased the resources again to 3GB with a timeout of 10 seconds (changing
the resources with the admin interface is not HA). This again showed the -1GB
available memory but this time it sent a preemption message to the AM (not
killing, just notifying that one of the mappers should be preempted).
# After 10 seconds, the RM killed the container.
# Decreased the resources to 2GB with a timeout of 0 seconds. This killed the
remaining mapper immediately.
# Increased the resources again to 4GB. The AM started the 2 mappers again.
# Decreased the resources to 2 GB again with a time out of 1 minute. This
triggered the notification to the AM for preemption.
# Increased the resources to 4GB again. This aborted the over commit protocol
and the job run for 5 more minutes with no issues.
All these tests are also covered by the unit test for both the Capacity
Scheduler and the Fair Scheduler.
> In case of long running tasks, reduce node resource should balloon out
> resource quickly by calling preemption API and suspending running task.
> -----------------------------------------------------------------------------------------------------------------------------------------------
>
> Key: YARN-999
> URL: https://issues.apache.org/jira/browse/YARN-999
> Project: Hadoop YARN
> Issue Type: Sub-task
> Components: graceful, nodemanager, scheduler
> Reporter: Junping Du
> Assignee: Íñigo Goiri
> Priority: Major
> Attachments: YARN-291.000.patch, YARN-999.001.patch,
> YARN-999.002.patch, YARN-999.003.patch, YARN-999.004.patch,
> YARN-999.005.patch, YARN-999.006.patch, YARN-999.007.patch
>
>
> In current design and implementation, when we decrease resource on node to
> less than resource consumption of current running tasks, tasks can still be
> running until the end. But just no new task get assigned on this node
> (because AvailableResource < 0) until some tasks are finished and
> AvailableResource > 0 again. This is good for most cases but in case of long
> running task, it could be too slow for resource setting to actually work so
> preemption could be used here.
--