> Would like to bring up the topic of when to close New features/ Improvements.
>
> I understand that we are closing new features/ improvements once we have 
> completed dependent subtasks like QA/ Documentation are done but we did not 
> call out dependency on defects explicitly.  Usually  we would not call it 
> done till we complete 1 cycle of QA and there are no outstanding P1 issues 
> exist as sometimes the implementation might not be in alignment with 
> requirements or do not meet supportability requirements.
>
> Given that we did not call out dependency and closure criteria explicitly, I 
> think we are treating feature done once QA/ Doc are done.
>
> However would like to propose that QA would reopen the new tasks/improvements 
> if implementation is not done as per the requirements or if there are serious 
> issues with the implementation ie like a blocker for a primary use case.
>

+1