I will be driving the branding effort from the marketing team.  I agree
design work needs to be done early. 04/04 is a good target.

On Wed, Feb 20, 2013 at 5:32 AM, Jürgen Schmidt <jogischm...@gmail.com>wrote:

> On 2/20/13 10:46 AM, Jürgen Schmidt wrote:
> > Hi,
> >
> > we make good progress with the sidebar work which is done on the branch.
> > The sidebar will be the most visible and important change for 4.0 (by
> > the way I like what I have seen so far). We come closer to the point
> > where we should talk about a more detailed schedule.
> >
> > I would like to start with the following proposal and still many steps
> > have to be defined in more detail.
> >
> > 03/01 function verification test will start, define test case, prepare
> > tests etc.
> > 04/04 integrate sidebar branch in trunk, other new features should be
> > finished by this date as well.
>
> I missed to add that the art work (logo, icons, etc. should be finished
> at this date as well)
>
> > 04/05 - 05/15 regression testing will be start on trunk
> > 04/05 - 05/15 bugfix and stabilization, no feature development
> > 04/08 - 05/15 translation -> I guessed ~5 weeks for updating the new
> > strings. This can change when we know exactly how many new strings we
> > will have. But translation for new languages can already work on the
> > existing po files for 3.4.1.
> > 05/21 RC1
> > 06/04 RC2
> > 06/18 RC3 (optional), can be GA already
> > 06/25 GA -> this should be our final target
> >
> >
> > This is a proposal based on the ongoing work that I no. Please let me
> > know if I missed something important.
> >
> > Regular developer builds 1/week + nightly builds
> >
> > Based on feedback and potential changes I will put this in the wiki
> later.
> >
> > Important is from my pov that we start talking about the improvements
> > that we make in public. It should be very clear for anybody where the
> > real important features and improvement for OpenOffice or derivatives
> > are coming from ;-)
> >
> >
> > Juergen
> >
>
>