Hello,
I checked the DSMcad and it shows the next scheduled operation is for 12/16/04 it should say 12/15/04. I killed the DSMCAD and restarted it, But it shows the next backup schedule 12/16/04. These backups runs everynight. I need to get this backup ready for 12/15/04. Anyone every have this problem with the schedule showing the wrong date? This is happening on the two Backup sessions that I cancelled this morning. AIX client 5.1.5 TSM 5.2.3.5 Thanks for any help! $ tail dsmwebcl.log Executing scheduled command now. 12/14/04 11:26:34 (dsmcad) Next operation scheduled: 12/14/04 11:26:34 (dsmcad) ------------------------------------------------------------ 12/14/04 11:26:34 (dsmcad) Schedule Name: MIDNIGHT 12/14/04 11:26:34 (dsmcad) Action: Incremental 12/14/04 11:26:34 (dsmcad) Objects: 12/14/04 11:26:34 (dsmcad) Options: 12/14/04 11:26:34 (dsmcad) Server Window Start: 00:00:01 on 12/16/04 12/14/04 11:26:34 (dsmcad) ------------------------------------------------------------ 12/14/04 11:26:34 (dsmcad) Waiting to be contacted by the server.