Hi,

I've created a Sprint and given it a full team with plenty of
capacity, created some Requirements, added some User Stories to them,
and Tasks to each of those, given Story Points to every story, given a
Remaining Time to each Task, and assigned all the User Stories to the
Sprint.

I get a Capacity line, but my Ideal Burndown line is flat and zero all
the way along.

The Sprint was due to start in a few days time. I changed the start
date to yesterday, but that had no effect.

Have I misssed something?

Thanks

Mark


--~--~---------~--~----~------------~-------~--~----~