On 12 May, 2009, at 18:08 , Pinksy wrote:
> We've just passed the first day of the Sprint, but no change in the > graph. That is really strange... did you restart the server? It can be a silly cache problem... the best way to invalidate the cache is to go to Admin/Agilo/General, and just push save, without changing anything (or try to enable/disable the Agilo UI) this will cause a reload of the config and of the cache as well. > We haven't got an Actual Burndown line yet. Do I need to complete some > tasks to get both the Actual Burndown line AND the Ideal Burndown > line? No actually it should be generated automatically also before the sprint starts, the actual line of course not ;-) > Interestingly, the Confirm Commitment button is still enabled. I > clicked it ther day before the Sprint, and the first day of the Sprint > (thinking it hadn't done anything). Should it still be enabled? Till the end of the first day... which is probably at 24:00 ;-) > Thanks for your help HTH > Mark. ANdreaT P.S: I am anyway hunting down a similar bug, it seems that is related to the date conversion in the cache as well, timestamps are always interpreted as UTC... so it may happen that you save something in the future... and the cache doesn't refresh... :? --~--~---------~--~----~------------~-------~--~----~ You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en -~----------~----~----~----~------~----~------~--~---

