Are you sticking with the same applications in Remedy?

If so I would recommend building the new box, installing Oracle, copying the 
data from Oracle 9 (I think the Oracle utility is called Data Pump or something 
like that), and installing ARS 7.5 as an upgrade.

Using the Oracle utility will also copy things like your Procedures/Functions 
and dbLinks to the new database.

The DBAs here used the utility when we moved our databases from a Sun RISC 
cluster w/Oracle 9i to a Sun x86 cluster w/Oracle 10g with no problems.

Fred

-----Original Message-----
From: Action Request System discussion list(ARSList) 
[mailto:[email protected]] On Behalf Of Brittain, Mark
Sent: Thursday, September 10, 2009 9:12 AM
To: [email protected]
Subject: Moving ARS 6.3 -> ARS 7.5

** 
HI All,
 
I am planning on moving from ARS 6.3 on SunOS 5.9, Oracle 9.2 to ARS 7.5 Oracle 
11g, Linux 5 (64-bit). Thought is to completely build the new box, install ARS 
7.5 and the move the data over to the new server.
 
Has anyone done this before? Any suggestions on the best way to move the data? 
Is there a better way?
 
Thanks
Mark Brittain
 

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor:[email protected] ARSlist: "Where the Answers Are"

Reply via email to