I've started to update the follow-up structure with links towards the
milestones, it's here http://community.hackit.cx/wiki/Tasks_follow-up

I've distinguished the iterations (weeks) from the milestones (objectives)
which should make things easier to follow, at least in the short term.

[Vlad] indeed it's much easier to follow the tasks for each iteration when
they are structured this way. One note though, you placed all dates for
"current & next iterations" in October and I think you meant September

 

 

Regarding the 2.2 : the idea is to switch completely HackIt to an OO
structure right ? How long do you estimate this would take ? If I follow the
current plan, for the coming iteration the training will be finished by
monday night (with the UML schema) which leaves 3 days to do the OO work -
I'd like to assess how many more days it would take, to see if it should be
considered as one iteration or less or more, and to see how we can come back
soon to a more structured iteration process :)

[Vlad] I'm on track with the training iteration. I finished going through
patters this evening and I will start the exercises tomorrow. One thing I
learned in the process is that switching to OO code will require a little
more than just packing the code into classes. I need to change the way I
think about the structure of code and the relation between different
elements. So I estimate at least a full iteration to swith to OO code.

Also, we must take into account the date of my departure to the US. I will
be leaving on Wednesday the 29th. 

I'm not sure what will be the agenda of our week in Montreal, but maybe it
can be a good time to work on the OO transition?

 

Once this 2.2 is completed, the next iterations can be used to complete the
1.2, which will consist in the replacement of AjaxIM by phpfreechat if I
followed correctly (should we plan some additional time for that ?), and the
2.0 and 2.1 for the completion of mission system.

[Vlad] I think phpfreechat should be fairly straight forward. Maybe 2 days
of work. 

Refactoring the code in OO will leave only the 2 bugs from 2.0. I already
made the change required for the IE6 bug, but unfortunately the laptop that
was running IE6 natively in our office has died and I need to find another
ie6 to test.

The other bug related to php warnings will require about 1 day of work

For 2.1 I estimate around 3 days. Do we agree that we go with a custom
implementation on this phase instead of AjaxIM?

 

Thx in advance for your inputs

D

_______________________________________________
Hackit Bar mailing list - [email protected]

Wiki:  http://community.hackit.cx/
List:  http://community.hackit.cx/ml/
Forum: http://community.hackit.cx/forum/
Ideas: http://community.hackit.cx/ideas/
IRC:   irc://irc.freenode.net/#politis

Reply via email to