Zitat von Claas Goltz <[email protected]>:

Hi,
is it technically possible to spool and despool at the same time?

For example (fictitious values)
given: 100GB Volume
50GB Spoolsize

- Tape job starts spooling 50 GB: 10 min
- writing (despooling) to tape: 10 min
- after despooling, spool the next 50gb: 10 min
- despooling 50gb: 10min
= total 40 minutes

if we despool and spool at the same time, we gain much time!

- spooling first part 50GB 10min
- despooling frist 50GB to tape, while spooling the next 50GB 10min
- despooling the next 50GB 10min
= total 30miutes

so that would be 1/3 faster. If you have large/much jobs that would gain enormous time.
Thanks
Claas

You should try to split the jobs. Different jobs can spool while another one is despooling. But be aware that you need a really fast spool area to feed a recent LTO and spool at the same time.

Regards

Andi


--
You received this message because you are subscribed to the Google Groups 
"bareos-users" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
For more options, visit https://groups.google.com/d/optout.

Reply via email to