-----Original Message-----
From: Alamaine <[EMAIL PROTECTED]>
To: CTRL <[EMAIL PROTECTED]>
Sent: Mon, 28 Apr 2008 10:37 am
Subject: [ctrl] Print Story: Investigators: Millions in Iraq contracts never 
finished on Yahoo! News






















    

            
Back to Story - Help

http://news.yahoo.com/s/ap/20080427/ap_on_go_ca_st_pe/iraq_reconstruction



Investigators: Millions in Iraq contracts never finished



By HOPE YEN, Associated Press Writer

Sun Apr 27, 6:42 PM ET



Millions of dollars of lucrative Iraq reconstruction contracts were never  

finished because of excessive delays, poor performance or other factors,  

including failed projects that are being falsely described by the U.S.  

government as complete, federal investigators say.



The audit released Sunday by Stuart Bowen Jr., the special inspector  

general for Iraq reconstruction, provides the latest snapshot of an uneven  

reconstruction effort that has cost U.S. taxpayers more than $100 billion.  

It also comes as several lawmakers have said they want the Iraqis to pick  

up more of the cost of reconstruction.



The special IG's review of 47,321 reconstruction projects worth billions  

of dollars found that at least 855 contracts were terminated by U.S.  

officials before their completion, primarily because of unforeseen factors  

such as violence and excessive costs. About 112 of those agreements were  

ended specifically because of the contractors' actual or anticipated poor  

performance.



In addition, the audit said many reconstruction projects were being  

described as complete or otherwise successful when they were not. In one  

case, the U.S. Agency for International Development contracted with  

Bechtel Corp. in 2004 to construct a $50 million children's hospital in  

Basra, only to "essentially terminate" the project in 2006 because of  

monthslong delays.



But rather than terminate the project, U.S. officials modified the  

contract to change the scope of the work. As a result, a U.S. database of  

Iraq reconstruction contracts shows the project as complete "when in fact  

the hospital was only 35 percent complete when work was stopped," said  

investigators in describing the practice of "descoping" as frequent.



"Descoping is an appropriate process but does mask problem projects to the  

extent they occur," the audit states.



Responding, USAID in the report said it disagreed that its descoping of  

the hospital project was "effectively a contract termination," but that it  

had changed the work because of escalating costs and security problems.  

Mark Tokola, the director of the Iraq transition assistance office, also  

responded that the database the IG's office reviewed of Iraq  

reconstruction contracts was incomplete.



Bowen's office said its review was preliminary and that it planned  

follow-up reviews to investigate descoping more closely. Investigators  

said they were also looking into whether contractors whose projects were  

terminated by the U.S. government due to inadequate performance might have  

been awarded new contracts later despite their poor records.



Investigators said the database they reviewed lacked full data on projects  

such as those done by USAID, the State Department, and those completed  

before 2006. But they said the figures cited in the report offered a  

baseline in terms of unfinished Iraq reconstruction contracts.



"Adding contract terminations from these (other) sources would certainly  

raise the number of terminated projects," the report states.



The audit comes amid renewed focus in recent months on potential abuse in  

contracting government-wide, such as Iraq reconstruction. Last year,  

congressional investigators said as much as $10 billion — or one in six  

dollars — charged by U.S. contractors for Iraq reconstruction were  

questionable or unsupported, and warned that significantly more taxpayer  

money was at risk.



In recent weeks, Sen. Ben Nelson, D-Neb., has been working with Sen. Evan  

Bayh, D-Ind., and Susan Collins, R-Maine, on legislation that would  

restrict future reconstruction dollars to loans instead of grants; require  

that Baghdad pay for fuel used by American troops and take over U.S.  

payments to predominantly Sunni fighters in the Awakening movement.



Danielle Brian, executive director of the watchdog group Project on  

Government Oversight, said the latest audit report points to significant  

U.S. taxpayer waste in current reconstruction efforts.



"The report paints a depressing picture of money being poured into failed  

Iraq reconstruction projects — contractors are killed, projects are blown  

up just before being completed, or the contractor just stops doing the  

work," she said.



Copyright © 2008 The Associated Press. All rights reserved. The  

information contained in the AP News report may not be published,  

broadcast, rewritten or redistributed without the prior written authority  

of The Associated Press. Copyright © 2008 Yahoo! Inc. All rights reserved.

Questions or Comments

Privacy Policy -Terms of Service - Copyright/IP Policy - Ad Feedback



-- 

Alamaine, IVe

Grand Forks, ND, US of A

~ ~ ~ ~ ~ ~ ~

"All are lunatics, but he who can analyze his delusion is called a

philosopher." - Ambrose Bierce (1842-1914)



"Being ignorant is not such a shame as being unwilling to learn." -

Poor Richard's Almanack, 1758 (Benjamin Franklin)

~~~~~~~

In accordance with Title 17 U.S.C. Section 107, the material is

distributed without profit to those who have expressed a prior

interest in receiving the included information for research and

educational purposes.



    
  

    
    
    
    




    
    
 

Reply via email to