I saw discussions from David J. that he was planning on branching 2.2
any day now, so it seems that your targets are too far out. Also, we
normally don't have a whole quarter between branching and releasing, but
should be something like one month after a branch for the target release.
-Donald
Rex Wang wrote:
HI
I notice a user in mail list who complained that the
http://cwiki.apache.org/GMOxPMGT/geronimo-22-release-status.html is out
of date.
>Ashwill, Steve (Facilities & Services)
>Hello,
>Can anyone tell me if there is a new roadmap in the works defining a
release schedule for version 2.2. We have been developing based on the
Geronimo 2.2 Release Status(OpenEJB 3.1), but if it will >not be
released in the next few months we may need to re-factor to 2.1.4. Our
support folks are a bit hesitant to deploy to production using a
snapshot version. I’ve checked
http://cwiki.apache.org>>>/GMOxPMGT/geronimo-22-release-status.html ,
but it has not been updated in a while.
>Any guessimation as to when and if 2.2 will be released would be
greatly appreciated.
>Thanks,
>Steve
I think at least the dates following should update, can anyone help?
Release Manager:
Proposed Branch/freeze date: 12/12/08 1/9/09 1Q2009 -> 3Q2009
Proposed Release Candidate: 1/9/09 1/16/09 1Q2009 -> 4Q2009
Proposed Release date: 1/15/09 1/30/09 1Q2009 -> 4Q2009
-Rex