I made some updates. I think I'm going to be the release manager
unless someone else volunteers.
thanks
david jencks
On Jun 15, 2009, at 5:45 AM, Donald Woods wrote:
I saw discussions from David J. that he was planning on branching
2.2 any day now, so it seems that your targets are too far out.
Also, we normally don't have a whole quarter between branching and
releasing, but should be something like one month after a branch for
the target release.
-Donald
Rex Wang wrote:
HI
I notice a user in mail list who complained that the http://cwiki.apache.org/GMOxPMGT/geronimo-22-release-status.html
is out of date.
>Ashwill, Steve (Facilities & Services)
>Hello,
>Can anyone tell me if there is a new roadmap in the works defining
a release schedule for version 2.2. We have been developing based
on the Geronimo 2.2 Release Status(OpenEJB 3.1), but if it will
>not be released in the next few months we may need to re-factor to
2.1.4. Our support folks are a bit hesitant to deploy to
production using a snapshot version. I’ve checked http://cwiki.apache.org
>>>/GMOxPMGT/geronimo-22-release-status.html , but it has not been
updated in a while.
>Any guessimation as to when and if 2.2 will be released would be
greatly appreciated.
>Thanks,
>Steve
I think at least the dates following should update, can anyone help?
Release Manager:
Proposed Branch/freeze date: 12/12/08 1/9/09 1Q2009 -> 3Q2009
Proposed Release Candidate: 1/9/09 1/16/09 1Q2009 -> 4Q2009
Proposed Release date: 1/15/09 1/30/09 1Q2009 -> 4Q2009
-Rex