Hey Christo
I was wondering if we could include KIP-1228 in the 4.2 release. We have
the required votes -- we just didn't officially close the vote yet.
I think we should also be able to implement it in time for the feature
freeze. What do you think?

Thanks,
Justine

On Thu, Oct 30, 2025 at 12:28 AM Christo Lolov <[email protected]>
wrote:

> Hello!
>
> We have now passed the KIP freeze date for 4.2.0. The next goal is the
> feature freeze on the 19th of November!
>
> Feel free to reachout on this thread if your changes are not getting
> traction to meet that date!
>
> Best,
> Christo
>
> On Wed, 22 Oct 2025 at 11:16, Christo Lolov <[email protected]>
> wrote:
> >
> > Hello!
> >
> > This is to bump the 4.2.0 thread to the top of the mailing list!
> >
> > The KIP freeze date is 1 week from today on the 29th of October.
> > Please ensure that you have the required number of binding votes for
> > your KIP by that date if you would like it included in 4.2.0.
> >
> > Best,
> > Christo
> >
> > On Thu, 2 Oct 2025 at 15:08, Mickael Maison <[email protected]>
> wrote:
> > >
> > > Hi,
> > >
> > > I think moving code freeze to December 10 makes sense.
> > > Many people will be off the last 2 weeks of December, so it's best to
> > > not have deadlines then.
> > >
> > > Thanks,
> > > Mickael
> > >
> > > On Thu, Oct 2, 2025 at 3:49 PM Christo Lolov <[email protected]>
> wrote:
> > > >
> > > > Hello!
> > > >
> > > > Thanks for the review!
> > > >
> > > > I am okay with pulling all dates by 2 weeks earlier in time (barring
> the
> > > > 7th of January one). If there are no objections to the new dates I
> will
> > > > update them in the plan tomorrow!
> > > >
> > > > Best,
> > > > Christo
> > > >
> > > > On Thu, 2 Oct 2025 at 07:14, Ismael Juma <[email protected]> wrote:
> > > >
> > > > > Hi Christo,
> > > > >
> > > > > Thanks for managing the release and for the proposed release plan.
> > > > >
> > > > > Given our desire to ship every 4 months, I think the proposed
> dates should
> > > > > be shifted a bit. The original plan was for 4.1 to ship in mid
> July and for
> > > > > 4.2 to ship in mid November. The former eventually shipped on
> September 2nd
> > > > > and with the current plan would probably result in 4.2 shipping in
> late
> > > > > January/early February. Given where we are, I would suggest
> something like:
> > > > >
> > > > > KIP Freeze: October 29 (Wednesday)
> > > > > Feature Freeze: November 19 (Wednesday)
> > > > > Code Freeze: December 10 (Wednesday)
> > > > > At least four weeks of stabilization will follow Code Freeze
> (taking
> > > > > holidays into account), meaning we expect to release no earlier
> than
> > > > > January 7 2026.
> > > > >
> > > > > Ideally, we'd get RC0 out before the holiday break and then
> complete the
> > > > > release by early/mid January.
> > > > >
> > > > > Thoughts?
> > > > >
> > > > > Ismael
> > > > >
> > > > > On Tue, Sep 30, 2025 at 6:09 AM Christo Lolov <
> [email protected]>
> > > > > wrote:
> > > > >
> > > > > > Hello!
> > > > > >
> > > > > > I would like to volunteer to be the release manager for the
> Apache Kafka
> > > > > > 4.2.0 release.
> > > > > >
> > > > > > If no one has any objections, you can find a proposed release
> plan at
> > > > > >
> https://cwiki.apache.org/confluence/display/KAFKA/Release+Plan+4.2.0.
> > > > > >
> > > > > > Thanks,
> > > > > > Christo
> > > > > >
> > > > >
>

Reply via email to