Summary: AtP of products should be adjusted when production run is
confirmed
Key: OFBIZ-5296
URL: https://issues.apache.org/jira/browse/OFBIZ-5296
Project: OFBiz
Issue Type: Improvement
Components: manufacturing, product
Affects Versions: SVN trunk
Reporter: Pierre Smits
When a production run is confirmed we know what is intended to go in the
production run (the components or ingredients aka the raw materials) and what
is intended to go out (the finished product).
Unlike with an order, the AtP (Availability to Promise) of the goods involved
does not get adjusted.
The result is that requirements for PO or even the PO itself get generated to
late (at the moment when QoH reaches minimum stock in stead of when AtP reaches
minimum stock).
Following scenarios need to be resolved:
1. On confirmation of the production run (action = Confirm), the AtP of the
product to be produced must increase and the AtP of materials needed must
decrease.
2. When production is running and materials have been released to the
production run, it is possible to return materials back to inventory. When
doing so, the AtP of the materials must be adjusted accordingly with the same
date-time and quantity as the returned materials.
3. When a production run has rejected end products the AtP of the end product
must be adjusted with the same date-time and quantity as the declaration of the
rejected product.
--