I just found a website by chance, which might be interesting for us.

It's another way of implementing project networks in spreadsheets, with
critical path analysis.

http://ite.pubs.informs.org/Vol3No3/Ragsdale/

By the way: in my opinion it is absolutely essential, that every task
has not only a predecessor, but also a successor! Otherwise this task
could delay without having an effect on the end-date of the project!

A good pm-tool should at least inform the user, if this is not the case.

CU Harald


---------------------------------------------------------------------