On Wed, 2005-11-09 at 18:45 +0100, Harald Ulver wrote:
Hi everyone,

I just found a website by chance, which might be interesting for us.

It's another way of implementing project networks in spreadsheets, with
critical path analysis.

http://ite.pubs.informs.org/Vol3No3/Ragsdale/

Great paper! Would be nice to make sure the Excel macros have an analog in Calc and to try and re-implement this in Calc.


By the way: in my opinion it is absolutely essential, that every task
has not only a predecessor, but also a successor! Otherwise this task
could delay without having an effect on the end-date of the project!

That's an interesting perspective but perhaps I've misunderstood your point. What about the very first task(s) and very last tasks in a project? Consider

Task A -+-> Task B
        |
        +-> Task C

In this example, Task A has no predecessor. Also, tasks B & C have no successors. Or this more complex configuration ...

Task A -+-> Task B
        |
        +-> Task C --+-> Task E
                     |
            Task D ->+

... in which case neither Task A nor Task D have predecessors.

Gil


A good pm-tool should at least inform the user, if this is not the case.

CU Harald


---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to