hello again,

We are making good progress. Once the outstanding patches are done we
are basically down to:

- Outstanding blocker bug fixes
- Dictionary encoding (I will take care of this)
- Test coverage for failure modes (malformed files)
- Organizing the public API
- Miscellaneous unit test coverage (we can use the code coverage
report as our guide
https://coveralls.io/github/apache/parquet-cpp?branch=master)
- Codebase scrubbing (compiler flags and signed/unsigned types -- I
will do this toward the end of the release)

I'd like to be done with the JIRAs we have scoped right now roughly
this time next week, and spend a few more days on code tidying, adding
some example scripts and general use / hardening before we cut the
release. Sound good?

Thanks
Wes

On Tue, Feb 16, 2016 at 9:46 AM, Wes McKinney <[email protected]> wrote:
> Thanks all.
>
> I'm gonna try to split the JIRAs into tracks so we can avoid working
> on patches in a suboptimal order. For example, many JIRAs cannot be
> completed until PARQUET-499 is done (Scanner tests and dictionary
> encoding rely on PLAIN encoding for all Parquet types).
>
> - Wes
>
> On Mon, Feb 15, 2016 at 9:13 PM, Majeti, Deepak <[email protected]> wrote:
>> This looks good to me as well.
>> With little more effort towards testing, March 1 should be a doable target.
>>
>> On 02/15/2016 07:11 PM, Julien Le Dem wrote:
>>> Looks good. I commented in the doc
>>>
>>> On Sun, Feb 14, 2016 at 9:18 AM, Aliaksei Sandryhaila <[email protected]>
>>> wrote:
>>>
>>>> The list looks reasonable. I've added PARQUET-530 to add support for LZO
>>>> compression.
>>>>
>>>> Not sure we'll be able to get everything done by March 1, but it's a good
>>>> target.
>>>>
>>>>
>>>>
>>>> On 02/13/2016 12:32 PM, Wes McKinney wrote:
>>>>
>>>>> Dear friends,
>>>>>
>>>>> I made a pass through the JIRAs and feature roadmap and listed out
>>>>> essential tasks for reaching a milestone that would merit a versioned
>>>>> code release, see:
>>>>>
>>>>>
>>>>> https://docs.google.com/document/d/1WyquzupLc3UkErO2OhqLJNQ9a84Cccc8LVUSuLQz39o/edit#
>>>>>
>>>>> I will be pressing for all of this to be completed with target date
>>>>> (for a parquet-cpp 0.1 RC) of March 1. I think with the current
>>>>> cadence and progress this should be achievable.
>>>>>
>>>>> It would be great if Aliaksei, Deepak, Julien, and Nong could briefly
>>>>> review the items and let me know if there are any blind spots / things
>>>>> we've missed?
>>>>>
>>>>> If we agree on the scope of the release and timeline, we should create
>>>>> ordered "tracks" of interrelated JIRAs as many of them depend on the
>>>>> others for functionality and unit test tools that will be created.
>>>>> This will reduce ambiguity about what needs doing next and reduce
>>>>> refactor churn / merge conflicts.
>>>>>
>>>>> Thank you
>>>>> Wes
>>>>>
>>>>
>>>
>>
>>
>> --
>> --