Here's my draft for this period's Incubator report for Taverna.. Sorry
I didn't have time to write a short one!


Edit at https://wiki.apache.org/incubator/September2016 or reply here.


Taverna is a domain-independent suite of tools used to design and execute
data-driven workflows.

Taverna has been incubating since 2014-10-20.

Three most important issues to address in the move towards graduation:

  1. Project maturity evaluation and graduation
  2. Complete IP/license review of unreleased repositories
  3. Further engaging user/devops community

Any issues that the Incubator PMC (IPMC) or ASF Board wish/need to be
aware of?

  Preparing to graduate.

How has the community developed since the last report?

  The community is moving towards graduation, by preparing a
  Graduation Maturity Assessment
  
https://cwiki.apache.org/confluence/display/TAVERNADEV/2016-03+Taverna+Graduation+Maturity+Assessment

  While we wished we could have released all of Taverna's git repositories
  through the Incubator before graduating, we realize that with limited
  developer time, getting all of them to a cleanly releasable state
  could remove focus from development of the core repositories.

  As we an important point of Incubator releases is to ensure the project
  understands the ASF release process, including release review and voting,
  IP management and licensing compatibility; as well as accepting
  contributions. We believe we have gained that after effectively 8
software releases
  https://archive.apache.org/dist/incubator/taverna/source/
  and 7 GSOC/student contributors.

  We have however identified the need for a License Review of the remaining
  git repositories that have not yet been formally released through the
  Apache Incubator (e.g. to ensure ASF file headers), which we are completing at
  https://cwiki.apache.org/confluence/display/TAVERNADEV/2016-09+License+review


  dev@taverna mailing lists stats:

  Jun 2016: 347
  Jul 2016: 221
  Aug 2015: 170

  users@taverna:

  Jun 2016: 4
  Jul 2016: 2
  Aug 2015: 4

  JIRA issues over last 90 days:

  34 created
  12 resolved

How has the project developed since the last report?

  The release of the Command Line and Engine was a major milestone
  for the project after joining Apache.

  Two successful GSOC students have added support for Docker
  and Common Workflow Language. A third student has further
  developed the Taverna Mobile app. Another student has contributed
  a plugin for OGC/GIS geographical web services.


Date of last release:

  2016-07-01 taverna-engine-3.1.0-incubating
  2016-07-01 taverna-common-activities-2.1.0-incubating
  2016-07-01 taverna-commandline-3.1.0-incubating


When were the last committers or PMC members elected?

  2015-12-04


On 4 September 2016 at 22:46,  <[email protected]> wrote:
> Dear podling,
>
> This email was sent by an automated system on behalf of the Apache
> Incubator PMC. It is an initial reminder to give you plenty of time to
> prepare your quarterly board report.
>
> The board meeting is scheduled for Wed, 21 September 2016, 10:30 am PDT.
> The report for your podling will form a part of the Incubator PMC
> report. The Incubator PMC requires your report to be submitted 2 weeks
> before the board meeting, to allow sufficient time for review and
> submission (Wed, September 07).
>
> Please submit your report with sufficient time to allow the Incubator
> PMC, and subsequently board members to review and digest. Again, the
> very latest you should submit your report is 2 weeks prior to the board
> meeting.
>
> Thanks,
>
> The Apache Incubator PMC
>
> Submitting your Report
>
> ----------------------
>
> Your report should contain the following:
>
> *   Your project name
> *   A brief description of your project, which assumes no knowledge of
>     the project or necessarily of its field
> *   A list of the three most important issues to address in the move
>     towards graduation.
> *   Any issues that the Incubator PMC or ASF Board might wish/need to be
>     aware of
> *   How has the community developed since the last report
> *   How has the project developed since the last report.
>
> This should be appended to the Incubator Wiki page at:
>
> http://wiki.apache.org/incubator/September2016
>
> Note: This is manually populated. You may need to wait a little before
> this page is created from a template.
>
> Mentors
> -------
>
> Mentors should review reports for their project(s) and sign them off on
> the Incubator wiki page. Signing off reports shows that you are
> following the project - projects that are not signed may raise alarms
> for the Incubator PMC.
>
> Incubator PMC



-- 
Stian Soiland-Reyes
http://orcid.org/0000-0001-9842-9718

Reply via email to