On 10/25/2010 02:51 PM, Vincent Massol wrote:
>
> On Oct 25, 2010, at 2:44 PM, Sergiu Dumitriu wrote:
>
>> On 10/25/2010 02:26 PM, Vincent Massol wrote:
>>>
>>> On Oct 25, 2010, at 2:21 PM, Sergiu Dumitriu wrote:
>>>
>>>> On 10/25/2010 12:32 PM, Vincent Massol wrote:
>>>>> Hi Sergiu,
>>>>>
>>>>> On Oct 21, 2010, at 1:08 AM, Sergiu Dumitriu wrote:
>>>>>
>>>>>> On 10/20/2010 09:31 AM, Vincent Massol wrote:
>>>>>>> The idea would be to have the following dates:
>>>>>>> - 2.6RC1: 1st of November 2010 (there's no M1)
>>>>>>> - 2.6 final: 18h of November
>>>>>>
>>>>>> I'd move the RC one week later.
>>>>>
>>>>> I actually think that 3 weeks is already almost too much actually,  since 
>>>>> the longest the likeliest people will introduce new features and not do 
>>>>> stabilization.
>>>>
>>>> WDYM 3 weeks?
>>>
>>> End to end, it's actually 3.5 weeks (I don't know why I put the date of 
>>> 18th of Nov. I think I wanted to put 15th initially but that slipped for 
>>> some reason... anyway let's keep 18th but with no slippage ;) ie we should 
>>> start releasing no later than the 15th, if not earlier ;)).
>>>
>>>> When did you start counting? 1st is next week, so just one
>>>> week between 2.5 and 2.6RC1. Also, trunk became 2.6 on the 14th, so that
>>>> would be only two weeks since the 2.6 version was introduced, I really
>>>> don't understand where the 3 weeks before the RC came. Note that I only
>>>> proposed moving the RC date, not the final date.
>>>
>>> I thought you were proposing to move the final date.
>>>
>>> I'm +0 to move only the RC by one week (although this gives less time for 
>>> stabilization and may result in more features being added in). A few days 
>>> instead of a week would be better. We need the stabilization time as much 
>>> as possible IMO. One week less means less stabilization on the new features 
>>> add for RC1.
>>
>> I'm +0 on either date, my statement was just a "if possible", since 18
>> days between a RC and the final release is a more than what we usually do.
>
> Indeed. I think I messed up the end date. what about a RC2 for the 8th of Nov.
>
> 2.6RC1: 1st of Nov
> 2.6RC2: 8th of Nov
> 2.6 final: start 15th, done for the 18th at latest

+1.

>>> Note that Raluca thinks she'll have finished the Recent Activity feature 
>>> for the 1st of Nov.
>>>
>>> Thanks
>>> -Vincent
>>>
>>>>> In addition this gives less chance for people to test the stabilization 
>>>>> release(s) (people only test when there are final releases).
>>>>>
>>>>> I'd really like to keep the proposed dates. Please let me know if it's ok 
>>>>> with you since you're the only one who voiced a concern on the date.


-- 
Sergiu Dumitriu
http://purl.org/net/sergiu/
_______________________________________________
devs mailing list
[email protected]
http://lists.xwiki.org/mailman/listinfo/devs

Reply via email to