Like Jack, the complexity of the project dictates how the requirements
are collected. Basically we do "other" and here is what we do:
1 UI person and designer get with biz owner to get high level
requirements for purpose of design elements.  At this point we may or
may not include a Business Analyst.
2. Initial wireframes/mockups are done and once okay'd by owner,
Business Analyst is incorporated and requirements for functionality
collected.
3. Project Manager is not incorporated until there is a completed set
of mock ups, HTML prototype and complete Biz Requirements doc version
1.0.

We are currently in discussed within our Interactive Design Dept
(where my position as Usability Coorindator is) of having a project
manager role added into the very early stages but this PM would not
be the one that would be responsible for actually driving the final
SDLC to production.


. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Posted from the new ixda.org
http://www.ixda.org/discuss?post=41112


________________________________________________________________
Welcome to the Interaction Design Association (IxDA)!
To post to this list ....... [email protected]
Unsubscribe ................ http://www.ixda.org/unsubscribe
List Guidelines ............ http://www.ixda.org/guidelines
List Help .................. http://www.ixda.org/help

Reply via email to