Hi, At $work we purchased a new mail server (Scalix) and need to migrate from our old mail server (CommunigatePro). We have 2500 accounts with the largest account about 4.2GB/53000 messages. Our problem is that in testing several of the imap migration programs available (mailutil, imapsync, MoveIMAPMail) we are looking at roughly 30 days to complete the migration which just is not going to work. One idea we have for doing this in a weekend is to have 30 processes running in parallel, but I am wondering what other people do to migrate to a new mail server in a large organization.
cheers, ski -- "When we try to pick out anything by itself, we find it connected to the entire universe" John Muir Chris "Ski" Kacoroski, [email protected], 206-501-9803 or ski98033 on most IM services _______________________________________________ Discuss mailing list [email protected] http://lopsa.org/cgi-bin/mailman/listinfo/discuss This list provided by the League of Professional System Administrators http://lopsa.org/