Hi Folks,
                 I see one of the limitation for Integration between MS
Project and TFS,when you  but share tasks it doesn't accept to publish
it, the only way to do it is to create a new resources with more than
one name then select it from the assigned to list.

For example :

1       Development Task        JOHN,ANTON  -> THIS IS NOT ACCEPTABLE
UNTIL YOU CREATE A RESOURCE WITH THIS NAME AND SELECT IT ON THE ASSIGNED
TO LIST.

I'm sure that all of you face this problem ? I want to make sure is
there any work around.

What I can see, that MS supposed to accept this with comma or semi colon
separated and insert multiple resources on the DB for the selected Work
Item, AM I wrong ?



Regards,
Moustafa Arafa
http://moustafa-arafa.blogspot.com
MCSD,MCTS,MCT,MVP



********************************NOTICE*************************************
This transmittal and/or attachments have been issued by Agility. The 
information contained here within may be privileged or confidential. If you are 
not the intended recipient, you are hereby notified that you have received this 
transmittal in error; any review, dissemination, distribution or copying of 
this transmittal is strictly prohibited. If you have received this transmittal 
and/or attachments in error, please notify us immediately by reply or by 
telephone (Tel. +965-809-222) and immediately delete this message and all its 
attachments. 


OzTFS.com - to unsubscribe from this list, send a message back to the list with 
'unsubscribe' as the subject.
Powered by mailenable.com - List managed by www.readify.net


Reply via email to