Don Sweeney No significant showstoppers in reference design reviews to date. Commissioning phase must be addressed, is 1 year commencing with first light. Need list of activities, cost estimate.* Construction vs. Operations funding is not an issue for DOE, only NSF. Bill Althouse is on medical leave, may be gone during proposal period. Don will get input, then select an author for the System Engineering/Overview section of the MREFC proposal in Bill's absence. Don will handle Monthly Progress Report editing: focus on new accomplishments, keep short, write "to the board".
Funding plan for the mirror is shaping up well, partners are stepping up. We have now strengthened our relationship with NCSA and we will consider them as the Archive Center (subject to board approval). Victor Krabbendam The NSF Senior Review will meet with Jeremy Mould and some other NOAO staff at NSF on September 6. It is unclear when Jeremy will be able to share what he learns. Sidney Wolff Working on Operations Plan for MREFC proposal, will be about 5 pages in the proposal plus cost estimate. Waiting for updated Ops Concept Documents from DM, EPO.* Tony Tyson International negotiations are going well. Saw Alex Szalay paper about distribution of SDSS data access, most frequent access is by an Oregon school district, lots of bandwidth for this. Both scientific users and EPO users represent significant workloads. Martin Nordby Working with Bill Althouse on Configuration Management process, extensions to docushare to support it. We will need this in place as part of Construction readiness cited in proposal. We will not use DOORS or "full aerospace" model. _______________________________________________ LSST-data mailing list [email protected] http://www.lsstmail.org/mailman/listinfo/lsst-data