Dear Dr. Zimmerman,

Thanks a lot for your help.

I want to minimize the cost of generation of one area subject to a fixed
value for the exchange between all the other areas. Shall I still work with
toggle_iflims.m as you suggested or you have some other suggestions?


Thanks a lot.

Best,

Henry




2013/11/26 Ray Zimmerman <[email protected]>

> Sorry, somehow my previous reply never got sent …
>
> So, what exactly do you want to optimize, if you are specifying the import
> and export? Are you saying you want to minimize cost of generation in both
> areas subject to a fixed value for the total exchange between the two
> areas? If so, the best you can do is constrain the net flow (DC
> approximation) to equal your specified value. The easiest thing is probably
> to start with the code in toggle_iflims.m and modify it to use an equality
> constraint instead of an inequality constraint on the interface flow.
>
> --
> Ray Zimmerman
> Senior Research Associate
> B30 Warren Hall, Cornell University, Ithaca, NY 14853
> phone: (607) 255-9645
>
>
>
> On Nov 26, 2013, at 10:43 AM, 车 <[email protected]> wrote:
>
> Hi Matpower users,
>
> Anybody have any ideas about how to calculate opf with the total import
> power and export power specified?
>
>
> Thanks a lot
>
> Lin
>
> On Nov 25, 2013, at 8:59, Henry Lin <[email protected]> wrote:
>
> Dear all,
>
> I am trying to use OPF with area interchange being specified. I know how
> much power is going to be import and export.
>
> How can I do it using Matpower?
>
>
> Thanks,
> Henry
>
>
>
>
>
>
>