We will need more information. What do you mean by “one part of the load becomes dispatchable”? Are you saying that you are having trouble specifying your loads as dispatchable or that only a few loads are dispatched at values less than their nominal value? Or that the loads that are curtailed are only partially curtailed?
We need to know what specifically you expected to see and how your result differs from that. Ray > On May 6, 2015, at 10:11 AM, Carlos Cruzat Hermosilla <[email protected]> > wrote: > > Hi All > > I am currently working with dispatchable loads in order to see the impact of > overloading the lines of the network. However when I run OPF just one part of > the total load becomes dispatchable which obviously affects my results, so > Does anybody knows what could be the reason? > > Thanks, > Carlos > > PD: The generation and lines capacities are enough to provide the required > energy.
