Please remove me from your mailing list

On Tue, Jan 7, 2020 at 11:27 PM Yang <[email protected]> wrote:

> Hi, everyone!
> I want to divide the 30 buses and 6 generators into 3 areas in case 30.m,
> in earlier messages, I find 'areas' don't affect the runopf(), but how in
> runopf_w_res? And what are differences between 'area' and 'zone'? After
> reading messages, I think areas are about buses and zones are about
> generators. Is it correct about my understand?
>
> I have two questions:
> First, I do some modify in in the t_case30_userfcns.m, gen1 and gen2 are
> in zone 1, gen5 and gen6 are in zone3, and gen3 and gen4 are in zone2. And
> every zone's reserve requirements are 30MW.
> " OutmailID: 124252370, List: 'matpower-l', MemberID: 85387903 SCRIPT:
> "reserve zones, element i, j is 1 if gen j is in zone i, 0 otherwise
> mpc.reserves.zones = [
>  1 1 0 0 0 0;
>  0 0 1 1 0 0;
>  0 0 0 0 1 1;
> ];
> " TCL MERGE ERROR ( 01/07/2020 23:27:04 ): "missing " reserve requirements
> for each zone in MW
> mpc.reserves.req   = [30; 30; 30];
>
> And results are:
> |
> Reserves                                                                 |
>
> ================================================================================
>  Gen   Bus   Status  Reserves   Price
>   #     #              (MW)     ($/MW)     Included in Zones ...
> ----  -----  ------  --------  --------   ------------------------
>   1      1      1      15.12      2.00     1
>   2      2      1      14.88      2.00     1
>   3     22      1      25.00      4.00     3
>   4     27      1       5.00      4.00     3
>   5     23      1      25.00      5.50     2
>   6     13      1       5.00      5.50     2
>                      --------
>             Total:     90.00              Total Cost: $305.99
> Zone  Reserves   Price
>   #     (MW)     ($/MW)
> ----  --------  --------
>   1     30.00      2.00
>   2     30.00      5.50
>   3     30.00      4.00
>
> ================================================================================
> |     Reserve
> Limits                                                           |
>
> ================================================================================
>  Gen   Bus   Status  Rmin mu     Rmin    Reserves    Rmax    Rmax mu
> Pmax mu
>   #     #             ($/MW)     (MW)      (MW)      (MW)     ($/MW)
> ($/MW)
> ----  -----  ------  --------  --------  --------  --------  --------
> --------
>   1      1      1        -        0.00     15.12     25.00       -
> 0.10
>   2      2      1        -        0.00     14.88     25.00       -
> -
>   3     22      1        -        0.00     25.00     25.00      1.00
> -
>   4     27      1        -        0.00      5.00     25.00       -
> -
>   5     23      1        -        0.00     25.00     25.00      0.50
> -
>   6     13      1        -        0.00      5.00     25.00       -
> -
>                                          --------
>                                 Total:     90.00
>
> And if I set every zone's reserve requirements are 20MW, the results are:
> |
> Reserves                                                                 |
>
> ================================================================================
>  Gen   Bus   Status  Reserves   Price
>   #     #              (MW)     ($/MW)     Included in Zones ...
> ----  -----  ------  --------  --------   ------------------------
>   1      1      1      15.12      2.00     1
>   2      2      1       4.88      2.00     1
>   3     22      1      20.00      3.00     2
>   4     27      1       0.00      3.00     2
>   5     23      1      20.00      5.00     3
>   6     13      1       0.00      5.00     3
>                      --------
>             Total:     60.00              Total Cost: $198.49
> Zone  Reserves   Price
>   #     (MW)     ($/MW)
> ----  --------  --------
>   1     20.00      2.00
>   2     20.00      5.00
>   3     20.00      3.00
>
> ================================================================================
> |     Reserve
> Limits                                                           |
>
> ================================================================================
>  Gen   Bus   Status  Rmin mu     Rmin    Reserves    Rmax    Rmax mu
> Pmax mu
>   #     #             ($/MW)     (MW)      (MW)      (MW)     ($/MW)
> ($/MW)
> ----  -----  ------  --------  --------  --------  --------  --------
> --------
>   1      1      1        -        0.00     15.12     25.00       -
> 0.10
>   2      2      1        -        0.00      4.88     25.00       -
> -
>   3     22      1        -        0.00     20.00     25.00       -
> -
>   4     27      1       1.00      0.00      0.00     25.00       -
> -
>   5     23      1        -        0.00     20.00     25.00       -
> -
>   6     13      1       0.50      0.00      0.00     25.00       -
> -
>                                          --------
>                                 Total:     60.00
>
> The prices for zones are different in the 30MW and 20MW, how do they
> change? And I'm not clear about Rmin mu, Rmax mu and Pmax mu.
>
> And the second question is I want to divide 30 buses into 3 areas or
> zones, in corresponding with generators. I find scale_load(), and I don't
> know if it is right, and if it is necessary to do this division. Also, if
> it is necessary, how to connect them?
> load_zone = zeros(30, 1);
> load_zone(1:9,11,28) = 1;
> load_zone(12:20,23) = 2;
> load_zone(10,21,22,24:27,29,30) = 3;
> opt = struct('pq', 'P', 'scale', 'QUANTITY');
> dmd = [30; 30; 30];
>
> Thanks a lot!
> Yang.
>
>
>
>

Reply via email to