Hello team,

On 24/11/2014 11:22, Chetan Mehrotra wrote:
> On Mon, Nov 24, 2014 at 4:36 PM, Davide Giannella <[email protected]> wrote:
>> Yes of course. Just for my scheduling when roughly do you think we'll be
>> in good shape for the cut?
> Would be bit conservative here. Probably by next Monday it should be done!
>
> Chetan Mehrotra
>
didn't see any cut performed while I was away so I was thinking of
cutting 1.1.3 tomorrow around 2pm GMT.

there are still 4 issue unresolved for 1.1.3

https://issues.apache.org/jira/issues/?jql=project%20%3D%20OAK%20AND%20fixVersion%20%3D%201.1.3%20AND%20resolution%20%3D%20Unresolved%20ORDER%20BY%20due%20ASC%2C%20priority%20DESC%2C%20created%20ASC

Can please the assignee let me know if more time is needed or move them
1.1.4?

Anyone aware of any middle-commit that could badly break the
functionality we should wait for before the cut?

Cheers
Davide