Hmm, that's not really what I envision as 'redundant' :-/

Is there an overview somewhere how this has been sorted for the other 
datacenters Linode uses? Are they better equipped?

--

> On 31 May 2015, at 16:09, Alex Forster via Outages <[email protected]> 
> wrote:
> 
> The redundancy was grid + generator. Unfortunately both failed. 
> 
> <signature-logo.png>          
> Alex Forster
> Network Engineer | Linode
> From: Scott Howard via Outages <[email protected]>
> Sent: Sunday, May 31, 2015 4:37AM
> To: Frank Bulk <[email protected]>
> Cc: Outages Mailing List <[email protected]>
> Subject: Re: [outages] Linode Fremont outage
> 
>> On Sat, May 30, 2015 at 8:04 PM, Frank Bulk via Outages 
>> <[email protected]> wrote:
>> Are suites tied to just one generator? 
>> 
>> 
>> Unless things have changed since I was last there, yes.  HE do not offer 
>> redundant power (at least, not at FMT2).
>> 
>> HE offer a great price point, but as the saying goes, you get what you pay 
>> for!
>> 
>>   Scott
>> 
>> 
>> _______________________________________________
>> Outages mailing list
>> 
>> [email protected]
>> https://puck.nether.net/mailman/listinfo/outages
> 
> _______________________________________________
> Outages mailing list
> [email protected]
> https://puck.nether.net/mailman/listinfo/outages

_______________________________________________
Outages mailing list
[email protected]
https://puck.nether.net/mailman/listinfo/outages

Reply via email to