You are currently determining the budget for your project. You have used the
bottom-up and PERT three point cost estimation techniques to estimate the
costs of your project work packages and rolled them up to a total project
cost of $50M. Your management has approved a $5M contingency reserve and a
$3M management reserve for this project.

What is your total cost baseline?

A.$50M
B.$53M
C.$55M
D.$58M

Hint: Management reserves are not a part of the project cost baseline.
------------------------------


All our free questions are updated to the latest *PMBOK® Guide* standard. Sign
up here to receive the questions via
email<http://www.free-pm-exam-questions.com>.
We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP















The answer is D.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to