The following PMP® exam sample question is taken from
http://www.free-pm-exam-questions.com - The answer is at the very bottom:


------------------------------
Which of the following tools & techniques are used to create a
Communications Management Plan?

A) Communications Requirements Analysis & Communications Technology.
B) Communications Skills & Lessons Learned Process.
C) Stakeholder Analysis & Project Scope Statement.
D) Communication Channels & Work Performance Information.
------------------------------


All our free questions are updated to the latest *PMBOK® Guide* standard. Sign
up here to receive the questions via
email<http://www.free-pm-exam-questions.com>.
We are a PMI Registered Education Provider.


Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ -
http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com














The answer is A.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/project-managment?hl=en.

Reply via email to