i All, The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------ You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (±5%). Approach B will most likely cost $25,000 (±40%). Which approach will you select if your project stakeholders' risk tolerances are low and if you want to select the less risky approach? A) Neither approach since they are not definitive estimates. B) Approach B since it ranges from $15,000 to $35,000. C) Approach A since it ranges from $47,500 to $52,500. D) A combination of approach A and B. ------------------------------ Hint: Estimates are never definitive. ------------------------------ All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider. Please click here <https://www.facebook.com/questions/10150305086634970/>for the correct answer and explanation. Until next time, Cornelius Fichtner, PMP President, OSP International LLC - http://www.project-management-prepcast.com -- You received this message because you are subscribed to the Google Groups "project managment" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/project-managment. For more options, visit https://groups.google.com/groups/opt_out.