Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam
Simulator (The answer is at the very bottom):

------------------------------

Which of the following tasks will not be done by the processes in the
planning process group?

A) Define and refine objectives
B) Plan the course of action required to attain the objectives.
C) Identify the project scope
D) Integrate people and other resources to carry out the project management
plan for the project

------------------------------
Hint: What is the function of the Direct and Manage Project Work process?
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by
at    <http://free.pm-exam-simulator.com>http://free.pm-exam-simulator.comand
try the PMP Exam Simulator free for 3 days. We also offer 110 free
questions at    <http://www.free-pm-exam-questions.com.>
http://www.free-pm-exam-questions.com. We are a PMI Registered Education
Provider.


Answer and Explanation:
The Correct Answer is D. Integrating resources is the task of the Direct
and Manage Project Work process that belongs to the executing process group.


Until Next Time,
Cornelius Fichtner, PMP
President, OSP International LLC
http://www.project-management-prepcast.com/<http://www.linkedin.com/redirect?url=http%3A%2F%2Fwww%2Eproject-management-prepcast%2Ecom%2F&urlhash=RJ0x&_t=tracking_anet>

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/project-managment.
For more options, visit https://groups.google.com/groups/opt_out.


Reply via email to