Hi All, The following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):
------------------------------ Mary is managing a data migration project. The project is in execution. The project’s current total Earned Value (EV) is $25,000 and the current Schedule Variance (SV) is $5,000. What is the project’s current Schedule Performance Index (SPI)? A) 1 B) 1.25 C) 0.83 D) 0.2 ------------------------------ Hint: You need 2 formulas to calculate the correct result. ------------------------------ All our questions are updated to the latest PMBOK® Guide standard. Stop by at <http://free.pm-exam-simulator.com> <http://free.pm-exam-simulator.com> http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at <http://www.free-pm-exam-questions.com.> <http://www.free-pm-exam-questions.com.> http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider. Until Next Time, Cornelius Fichtner, PMP President, OSP International LLC http://www.project-management-prepcast.com/ Answer and Explanation: The Correct Answer is B. SPI = EV/PV. We know that EV = $25,000, but not the PV. This means we first have to determine the current PV in order to determine the current SPI. -- You received this message because you are subscribed to the Google Groups "project managment" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/project-managment. For more options, visit https://groups.google.com/groups/opt_out.