Mary is managing a data migration project. The project is in execution. The
project’s current total Earned Value (EV) is $25,000 and the current
Schedule Variance (SV) is $5,000. What is the project’s current Schedule
Performance Index (SPI)?

A) 1
B) 1.25
C) 0.83
D) 0.2
------------------------------

Hint: You need 2 formulas to calculate the correct result.

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by
at   <http://free.pm-exam-simulator.com> <http://free.pm-exam-simulator.com>
http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3
days. We also offer 110 free questions at
<http://www.free-pm-exam-questions.com.>
  <http://www.free-pm-exam-questions.com.>
http://www.free-pm-exam-questions.com. We are a PMI Registered Education
Provider.

Until Next Time,
Cornelius Fichtner, PMP
President, OSP International LLC
http://www.project-management-prepcast.com/

Answer and Explanation:
The Correct Answer is B. SPI = EV/PV. We know that EV = $25,000, but not
the PV. This means we first have to determine the current PV in order to
determine the current SPI.

-- 
You received this message because you are subscribed to the Google Groups 
"project managment" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/project-managment.
For more options, visit https://groups.google.com/groups/opt_out.

Reply via email to