Line side tap with a fusable disconnect or a new service with dual main load breakers. ( used in ag applications) There may be other requirements also depending on AHJ Jerry On Sep 25, 2015 3:11 AM, "gary easton" <[email protected]> wrote:
> Hello Wrenches, > What are folks doing when installing 100A plus of solar into a 200A > service? > > -- > Gary Easton > Appalachian Renewable Power > Stewart, Ohio 45778 > NABCEP Certified Solar PV > > T: 740-277-8498 > www.arp-solar.com > > “First they ignore you. Then they laugh at you. Then they fight you. Then > you win.” > ~Ghandi > > > _______________________________________________ > List sponsored by Redwood Alliance > > List Address: [email protected] > > Change listserver email address & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > > List-Archive: > http://www.mail-archive.com/[email protected]/maillist.html > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm > > Check out or update participant bios: > www.members.re-wrenches.org > > >
_______________________________________________ List sponsored by Redwood Alliance List Address: [email protected] Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/[email protected]/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org