Line side tap with a fusable disconnect or a new service with dual main
load breakers. ( used in ag applications) There may be other requirements
also depending on AHJ
Jerry
On Sep 25, 2015 3:11 AM, "gary easton" <[email protected]> wrote:

> Hello Wrenches,
> What are folks doing when installing 100A plus of solar into a 200A
> service?
>
> --
> Gary Easton
> Appalachian Renewable Power
> Stewart, Ohio 45778
> NABCEP Certified Solar PV
>
> T: 740-277-8498
>  www.arp-solar.com
>
> “First they ignore you. Then they laugh at you. Then they fight you. Then
> you win.”
> ~Ghandi
>
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: [email protected]
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive:
> http://www.mail-archive.com/[email protected]/maillist.html
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> www.members.re-wrenches.org
>
>
>
_______________________________________________
List sponsored by Redwood Alliance

List Address: [email protected]

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/[email protected]/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to