On Sunday 12 December 2010 5:49:56 pm Ian Monroe wrote:
> On Thu, Dec 9, 2010 at 12:28, Allen Winter <[email protected]> wrote:
> > Howdy all,
> >
> > This is a formal request from the KDEPIM team to add a 2 week delay to the
> > 4.6 release schedule and to use that extra 2 weeks to add another beta 
> > release.
> >
> > We really need the extra time; data migration is still taking time to get 
> > right.
> >
> > This would also delay the Git transition for KDEPIM and others the same 2 
> > weeks.
> >
> > The proposed change would look like this:
> >
> > # 1.11 Monday, January 3, 2011: Tagging Freeze for Release Candidate 1 <<== 
> > Git Migration
> > # 1.12 Monday, January 3 2011: Hard API Freeze
> > # 1.13 Monday, January 3, 2011: Hard Message Freeze
> > # 1.14 Monday, January 3, 2011: Artwork and Bindings Freeze
> > # 1.15 Tuesday, January 4, 2011: Release Candidate 1 Tagging
> > # 1.16 Wednesday, January 5, 2011: Release Candidate 1 Release
> > # 1.17 Monday, January 17, 2011: Tagging Freeze for Release Candidate 2
> > # 1.18 Tuesday, January 18, 2011: Release Candidate 2 Tagging
> > # 1.19 Wednesday, January 19, 2011: Release Candidate 2 Release
> > # 1.20 Wednesday, February 2, 2011: Final Tag
> > # 1.21 Wednesday, February 9, 2011: Release
> >
> > Thoughts?
> 
> What's going on with this?
> 
I'm waiting for objections.

So far we don't have any objections.  If there are no objections in day or so
I will offiically change the release schedule.