Re: Hive 0.9 release

2012-04-09 Thread Ashutosh Chauhan
As per the plan I am going to create a branch now. Please hold off any
commits till I send an email for all-clear.

Thanks,
Ashutosh

On Fri, Apr 6, 2012 at 15:00, Owen O'Malley omal...@apache.org wrote:

 I think we also need to get the RAT report cleaned up. Apache projects
 aren't supposed to release while they have files without the Apache
 header. I've filed HIVE-2930 to fix all of the issues.

 While working on it, I found that one of the files was added by
 HIVE-2246. HIVE-2246 was contributed by Sohan Jain, who hasn't filed
 an ICLA, and doesn't have the jira box checked for contribution. Does
 someone know him and can ask him to state on the jira that he intended
 to contribute it? Failing that, I believe he was working at Facebook
 at the time, so someone else who is still there can upload the patch
 to the jira?

 All of this brings up a challenge in that Phabricator and the Apache
 review tool upload patches to jira without providing a way to check
 the contribute to Apache box. Without the checkbox we should only
 commit patches from people who have filed ICLAs. Is there a way to add
 an option the arc command that will check the box? Even having it
 *always* check the box is better than having it not check the box.
 (Although it should warn users that it is doing so.)

 Thoughts?

 -- Owen



Re: Hive 0.9 release

2012-04-09 Thread Ashutosh Chauhan
All-clear. Trunk is now open for commits.

Since HIVE-2929 have resulted in intermittent test failures. (See,
HIVE-2937), I branched right before HIVE-2929.  Additionally, I merged in
HIVE-2764 in 0.9

I also added version 0.10 on jira, so any commits on trunk now must have
0.10 as fix version.

Thanks,
Ashutosh

On Mon, Apr 9, 2012 at 17:01, Ashutosh Chauhan hashut...@apache.org wrote:

 As per the plan I am going to create a branch now. Please hold off any
 commits till I send an email for all-clear.

 Thanks,
 Ashutosh


 On Fri, Apr 6, 2012 at 15:00, Owen O'Malley omal...@apache.org wrote:

 I think we also need to get the RAT report cleaned up. Apache projects
 aren't supposed to release while they have files without the Apache
 header. I've filed HIVE-2930 to fix all of the issues.

 While working on it, I found that one of the files was added by
 HIVE-2246. HIVE-2246 was contributed by Sohan Jain, who hasn't filed
 an ICLA, and doesn't have the jira box checked for contribution. Does
 someone know him and can ask him to state on the jira that he intended
 to contribute it? Failing that, I believe he was working at Facebook
 at the time, so someone else who is still there can upload the patch
 to the jira?

 All of this brings up a challenge in that Phabricator and the Apache
 review tool upload patches to jira without providing a way to check
 the contribute to Apache box. Without the checkbox we should only
 commit patches from people who have filed ICLAs. Is there a way to add
 an option the arc command that will check the box? Even having it
 *always* check the box is better than having it not check the box.
 (Although it should warn users that it is doing so.)

 Thoughts?

 -- Owen





Re: Hive 0.9 release

2012-04-06 Thread Ashutosh Chauhan
Hi All,

Seems like we have an agreement. So, unless someone has other ideas, I will
cut the branch for 0.9 on 4/9. Below is the consolidated list which people
have requested for 0.9, so as and when these gets checked-in trunk, we will
merge it back in 0.9.

2084
2764
538
2646
2777
2585
2883
2926

Thanks,
Ashutosh

On Mon, Apr 2, 2012 at 19:02, Thomas Weise t...@yahoo-inc.com wrote:

 Would be great to get HIVE-2646 included.

 Thanks,
 Thomas


 On 4/2/12 6:59 PM, Ashutosh Chauhan hashut...@apache.org wrote:

  Here is a list of jiras which I plan to get in 0.9.
 
  HIVE-2084
  HIVE-2822
  HIVE-2764
  HIVE-538
 
  I will work with authors of these patches to see these can get in.
 Others,
  please feel free to add this list.
 
  Thanks,
  Ashutosh
 
  On Mon, Apr 2, 2012 at 18:39, Carl Steinbach c...@cloudera.com wrote:
 
  I'm +1 on doing an 0.9.0 release, but would also like to suggest that we
  put together a list of 0.9.0 blockers before cutting the release
 branch. In
  the past we have frequently underestimated the amount of work required
 to
  get trunk into a releasable state, with the consequence that we up
 wasting
  time doing a lot of backports from trunk to the release branch. It
 would be
  great if we could avoid all of that this time around.
 
  Thanks.
 
  Carl
 
  On Mon, Apr 2, 2012 at 6:33 PM, Ashutosh Chauhan hashut...@apache.org
  wrote:
 
  Hi all,
 
  Branch for 0.8-r2 was created on Dec 7, almost four months ago. Between
  then and now lots of cool stuff has landed in trunk waiting to be
  released
  and get to users. I think its a good time now to get the ball rolling
 for
  0.9 release.   If this sounds good, I would propose to cut a branch for
  0.9
  later this week. Then we can focus on stabilizing the branch and
  subsequent
  release from it.  Thoughts?
 
  Thanks,
  Ashutosh
 
 




Re: Hive 0.9 release

2012-04-06 Thread Hugo Trippaers
Would it be possible/feasible to include 2910?

Cheers,

Hugo

Verstuurd vanaf mijn iPhone

Op 6 apr. 2012 om 21:18 heeft Ashutosh Chauhan hashut...@apache.org het 
volgende geschreven:

 Hi All,
 
 Seems like we have an agreement. So, unless someone has other ideas, I will
 cut the branch for 0.9 on 4/9. Below is the consolidated list which people
 have requested for 0.9, so as and when these gets checked-in trunk, we will
 merge it back in 0.9.
 
 2084
 2764
 538
 2646
 2777
 2585
 2883
 2926
 
 Thanks,
 Ashutosh
 
 On Mon, Apr 2, 2012 at 19:02, Thomas Weise t...@yahoo-inc.com wrote:
 
 Would be great to get HIVE-2646 included.
 
 Thanks,
 Thomas
 
 
 On 4/2/12 6:59 PM, Ashutosh Chauhan hashut...@apache.org wrote:
 
 Here is a list of jiras which I plan to get in 0.9.
 
 HIVE-2084
 HIVE-2822
 HIVE-2764
 HIVE-538
 
 I will work with authors of these patches to see these can get in.
 Others,
 please feel free to add this list.
 
 Thanks,
 Ashutosh
 
 On Mon, Apr 2, 2012 at 18:39, Carl Steinbach c...@cloudera.com wrote:
 
 I'm +1 on doing an 0.9.0 release, but would also like to suggest that we
 put together a list of 0.9.0 blockers before cutting the release
 branch. In
 the past we have frequently underestimated the amount of work required
 to
 get trunk into a releasable state, with the consequence that we up
 wasting
 time doing a lot of backports from trunk to the release branch. It
 would be
 great if we could avoid all of that this time around.
 
 Thanks.
 
 Carl
 
 On Mon, Apr 2, 2012 at 6:33 PM, Ashutosh Chauhan hashut...@apache.org
 wrote:
 
 Hi all,
 
 Branch for 0.8-r2 was created on Dec 7, almost four months ago. Between
 then and now lots of cool stuff has landed in trunk waiting to be
 released
 and get to users. I think its a good time now to get the ball rolling
 for
 0.9 release.   If this sounds good, I would propose to cut a branch for
 0.9
 later this week. Then we can focus on stabilizing the branch and
 subsequent
 release from it.  Thoughts?
 
 Thanks,
 Ashutosh
 
 
 
 


Re: Hive 0.9 release

2012-04-06 Thread Owen O'Malley
I think we also need to get the RAT report cleaned up. Apache projects
aren't supposed to release while they have files without the Apache
header. I've filed HIVE-2930 to fix all of the issues.

While working on it, I found that one of the files was added by
HIVE-2246. HIVE-2246 was contributed by Sohan Jain, who hasn't filed
an ICLA, and doesn't have the jira box checked for contribution. Does
someone know him and can ask him to state on the jira that he intended
to contribute it? Failing that, I believe he was working at Facebook
at the time, so someone else who is still there can upload the patch
to the jira?

All of this brings up a challenge in that Phabricator and the Apache
review tool upload patches to jira without providing a way to check
the contribute to Apache box. Without the checkbox we should only
commit patches from people who have filed ICLAs. Is there a way to add
an option the arc command that will check the box? Even having it
*always* check the box is better than having it not check the box.
(Although it should warn users that it is doing so.)

Thoughts?

-- Owen


Hive 0.9 release

2012-04-02 Thread Ashutosh Chauhan
Hi all,

Branch for 0.8-r2 was created on Dec 7, almost four months ago. Between
then and now lots of cool stuff has landed in trunk waiting to be released
and get to users. I think its a good time now to get the ball rolling for
0.9 release.   If this sounds good, I would propose to cut a branch for 0.9
later this week. Then we can focus on stabilizing the branch and subsequent
release from it.  Thoughts?

Thanks,
Ashutosh


Re: Hive 0.9 release

2012-04-02 Thread Ashutosh Chauhan
Here is a list of jiras which I plan to get in 0.9.

HIVE-2084
HIVE-2822
HIVE-2764
HIVE-538

I will work with authors of these patches to see these can get in. Others,
please feel free to add this list.

Thanks,
Ashutosh

On Mon, Apr 2, 2012 at 18:39, Carl Steinbach c...@cloudera.com wrote:

 I'm +1 on doing an 0.9.0 release, but would also like to suggest that we
 put together a list of 0.9.0 blockers before cutting the release branch. In
 the past we have frequently underestimated the amount of work required to
 get trunk into a releasable state, with the consequence that we up wasting
 time doing a lot of backports from trunk to the release branch. It would be
 great if we could avoid all of that this time around.

 Thanks.

 Carl

 On Mon, Apr 2, 2012 at 6:33 PM, Ashutosh Chauhan hashut...@apache.org
 wrote:

  Hi all,
 
  Branch for 0.8-r2 was created on Dec 7, almost four months ago. Between
  then and now lots of cool stuff has landed in trunk waiting to be
 released
  and get to users. I think its a good time now to get the ball rolling for
  0.9 release.   If this sounds good, I would propose to cut a branch for
 0.9
  later this week. Then we can focus on stabilizing the branch and
 subsequent
  release from it.  Thoughts?
 
  Thanks,
  Ashutosh
 



Re: Hive 0.9 release

2012-04-02 Thread Thomas Weise
Would be great to get HIVE-2646 included.

Thanks,
Thomas


On 4/2/12 6:59 PM, Ashutosh Chauhan hashut...@apache.org wrote:

 Here is a list of jiras which I plan to get in 0.9.
 
 HIVE-2084
 HIVE-2822
 HIVE-2764
 HIVE-538
 
 I will work with authors of these patches to see these can get in. Others,
 please feel free to add this list.
 
 Thanks,
 Ashutosh
 
 On Mon, Apr 2, 2012 at 18:39, Carl Steinbach c...@cloudera.com wrote:
 
 I'm +1 on doing an 0.9.0 release, but would also like to suggest that we
 put together a list of 0.9.0 blockers before cutting the release branch. In
 the past we have frequently underestimated the amount of work required to
 get trunk into a releasable state, with the consequence that we up wasting
 time doing a lot of backports from trunk to the release branch. It would be
 great if we could avoid all of that this time around.
 
 Thanks.
 
 Carl
 
 On Mon, Apr 2, 2012 at 6:33 PM, Ashutosh Chauhan hashut...@apache.org
 wrote:
 
 Hi all,
 
 Branch for 0.8-r2 was created on Dec 7, almost four months ago. Between
 then and now lots of cool stuff has landed in trunk waiting to be
 released
 and get to users. I think its a good time now to get the ball rolling for
 0.9 release.   If this sounds good, I would propose to cut a branch for
 0.9
 later this week. Then we can focus on stabilizing the branch and
 subsequent
 release from it.  Thoughts?
 
 Thanks,
 Ashutosh