Hi,
We have two ESS800 in two locations with PPRC v2. We plan to power-off
ESS_A (primary) for realocation (1-2 hours). For this period of time
system and application will be stopped.
During this time we don’t plan to start system in secondary location, so
there will be no update on ESS_B
We have two ESS800 in two locations with PPRC v2. We plan to power-off
ESS_A (primary) for realocation (1-2 hours). For this period of time
system and application will be stopped.
During this time we don’t plan to start system in secondary location, so
there will be no update on ESS_B
-- snip --
We have two ESS800 in two locations with PPRC v2. We plan to power-off
ESS_A (primary) for realocation (1-2 hours). For this period of time
system and application will be stopped.
During this time we don’t plan to start system in secondary location, so
there will be no update on
On Tue, 18 Oct 2005 13:48:37 +0200, TISLER Zaromil
[EMAIL PROTECTED] wrote:
Method 1:
- Stopping all systems leaves the volumes in sync. You don't have to do
anything.
Method 2:
- before you power down a box, Delete pair
- after the relocation establish nocopy
Well agree with method 1 ..