Timothy Sipples wrote:
The z14 ZR1 does not support ESA/390 IPLs, so please check your inventory
of IPL'able items such as DFSMS recovery utilities, z/VM installation DVDs,
ZZSA, and old Linux distributions, as applicable, to make sure they're
modern enough. There's one available workaround for
W dniu 2018-07-11 o 18:00, Jake Anderson pisze:
Absolutely we have looked into that aspect.. however wanted to know if
there was any known issues
Jake,
You plan to perform a jump from z114 to z14. That means z11->z14 with no
z12, z13.
Is it risky? No, I don't think so. For every hardware
Dana Mitchell wrote:
>We are currently on z114's and will probably migrate to z14
>zr1's, and the coupling link situation is our biggest stumbling
>block. Since there is no common coupling link available between
>z114-z14, it will require us to move the entire plex at once,
>not rolling onto
Absolutely we have looked into that aspect.. however wanted to know if
there was any known issues
Thanks again for all the great answer
On Wed 11 Jul, 2018, 6:27 PM R.S., wrote:
> W dniu 2018-07-11 o 06:07, Jake Anderson pisze:
> > Hi
> >
> > Has anyone moved your z hardware from z114 to z14
W dniu 2018-07-11 o 06:07, Jake Anderson pisze:
Hi
Has anyone moved your z hardware from z114 to z14 ?
Any gotchas and how was your migration experience ?
We are at zOS 2.2 with z114.
People gave you wise answers, however to complement it: check your PTFs.
z/OS 2.2 should be patched to
We are not in sysplex so I hope it should not be a concern ?
On Wed 11 Jul, 2018, 5:04 PM Parwez Hamid, wrote:
> The old SAPR process been 'replaced' by the TDA. The SAPR Guide is no
> longer produced. Its just the Must Read doc and actually covers most of the
> H/W and OS planning.
>
>
The old SAPR process been 'replaced' by the TDA. The SAPR Guide is no longer
produced. Its just the Must Read doc and actually covers most of the H/W and OS
planning.
--
For IBM-MAIN subscribe / signoff / archive access
We are currently on z114's and will probably migrate to z14 zr1's, and the
coupling link situation is our biggest stumbling block. Since there is no
common coupling link available between z114-z14, it will require us to move
the entire plex at once, not rolling onto new hardware, one LPAR
Aren't SAPRs done anymore? Semi-formal process review of hardware changes,
software level sets, IO changes, environmentals to include POWER and BTU's and
who's responsible.
In a message dated 7/11/2018 3:50:43 AM Central Standard Time,
parwez_ha...@hotmail.com writes:
Assuming you are
Assuming you are migrating to a z14 ZR1, comparing to the z114, there are a
number of things you should be aware of to do with size of the system, power
requirements, features NOT supported etc etc. As I can't attach any docs to
this reply, I suggest you speak to your BP or IBM person and ask
channel: https://www.youtube.com/channel/UCu_65HaYgksbF6Q8SQ4oOvA
From: Tom Brennan
To: IBM-MAIN@LISTSERV.UA.EDU
Date: 11/07/2018 09:15
Subject: Re: Z114 to z14 experience any ?
Sent by:IBM Mainframe Discussion List
Can I assume the target is a z14-ZR1 single-frame? I've
Thanks Tom we will be migrating to z14 zr1. Thanks for the inputs
On Wed 11 Jul, 2018, 12:15 PM Tom Brennan,
wrote:
> Can I assume the target is a z14-ZR1 single-frame? I've yet to see one
> installed, but hopefully I'll get to see one replace a z10BC next week.
> A few hardware things I can
Thanks and any technical challenges ?
On Wed 11 Jul, 2018, 10:28 AM ITschak Mugzach, wrote:
> Have heard some clients complains about msu raised. This mean that you may
> pay more than you used.
>
> ITachak
>
> בתאריך יום ד׳, 11 ביולי 2018, 6:07, מאת Jake Anderson <
>
Have heard some clients complains about msu raised. This mean that you may
pay more than you used.
ITachak
בתאריך יום ד׳, 11 ביולי 2018, 6:07, מאת Jake Anderson <
justmainfra...@gmail.com>:
> Hi
>
> Has anyone moved your z hardware from z114 to z14 ?
>
> Any gotchas and how was your migration