there was a proposal a cycle or two ago that wanted all of these components addressed. The TC said that was not necessary.

The value of reading the ROP/ROC for REJECTED items is that it provides a lot of information on the INTENT since all rejected items need a reason. Granted some are more educational than others but overall it is a seldom tapped resource.

Roland

On Jan 20, 2009, at 1:22 PM, Chris Cahill wrote:

Except supposedly the fabrication process locally destroys the coatings. And the other components like weld-o-lets, heads, valves and mech- tees are
not coated.