Try the floor.landing.  Both current IBC and NFPA 14 cite floor landing or
smoke-proof vestibule as "preferred location".

Steve Leyton
Protection Design & Consulting

Bob <[email protected]> wrote:

Every time I have a combination stand pipe / system riser there is an
awkward transition between the intermediate landing and the floor above.
What type of arrangements are others of you using to make this transition
smoother?  Any suggestions and direction is welcome.

Thanks,

Bob Knight, CET III
208-318-3057
www.firebyknight.com





_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

Reply via email to