That's an old one. 3/4 - one head 1"- two heads 1-1/4"- 3 heads 1-1/2"-5 heads  
2"- 7 heads. From memory. In the old textile mills in New England FM had a 
program where the 3/4" was replaced with 1".  Removed the 1x3/4x1/2 tee 
replaced it with 1x1x1/2 and replaced the 3/4" length of pipe keeping the same 
spacing. Did thousands of them in the 70's. 

Mike C

Sent from my iPhone

> On Dec 31, 2014, at 12:10 PM, Vince Sabolik <[email protected]> wrote:
> 
> Hi Forum (and Happy New Year!)
> 
> Does anyone have a pipe schedule that ends
> with ¾" pipe, and includes all the big pipe?
> 
> Sure would appreciate it!
> 
> 
> West Tech Fire Protection, Inc.
> 11351 Pearl Road
> Suite 102
> Strongsville, Ohio 44136
> T 440 238-4800    F 440 238-4876
> _______________________________________________
> Sprinklerforum mailing list
> [email protected]
> http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to