We have a contractor that is refusing to flush the UG pipe prior to tie in 
because he "has never done it in 20 years". I can find something in NFPA 13R 
that requires a flush  but nothing in 13D...... Anyone have any insight on why 
its not required in 13D?

Rocci Cetani III, CET
Senior Designer
Water-Based Fire Protections Systems Layout, Nicet Level III

Northern California Fire Protection Services Inc.
16840 Joleen Way Bldg. A
Morgan Hill, CA 95037
P-(408) 776-1580 EXT.1010
F-(408) 776-1590


[email protected]<mailto:[email protected]>
www.norcalfire.com<http://www.norcalfire.com/>

CONFIDENTIALITY NOTICE: This message and any document accompanying it may 
contain confidential information
belonging to the sender. The information is intended only for the use of 
individual or entity named above. If you are not the intended recipient, or the 
employee or agent responsible to deliver this message to the intended 
recipient, you are hereby notified that any disclosure, copying or taking of 
any action in reliance on the contents of this information is strictly 
prohibited. If you have received this transmission in error, please immediately 
notify us by telephone to arrange for return of the documents.

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org
  • 13D UG f... Rocci 3 Cetani via Sprinklerforum
    • RE:... Matt Grise via Sprinklerforum
      • ... Steele, Andrew via Sprinklerforum
        • ... Jones, William - Fire Plans Examiner/Inspector via Sprinklerforum
    • Re:... J H via Sprinklerforum
    • RE:... Prahl, Craig/GVL via Sprinklerforum
      • ... Ken Wagoner via Sprinklerforum

Reply via email to