Hi all,
Here is the latest update about Mehdipatnam school class room construction. Today Slab construction is happening under the supervision of SSA engineers. Mr.Laxmaiah,AE,SSA called me and informed me about the work. Though there was little delay, I am happy that we are progressing on the work. I spoke to contractor to complete the work by Aug 15th, But It will be difficult, atleast they need to leave 2 weeks for curing, so building walls and windows/doors etc will take some more time. Given the phase of the work, it might take another 1 month+ for the actual completion. Meanwhile, I have submitted a request letter to SSA to release funds from their contribution (80%) based on the work status. Thanks harinath