On 21/10/13 12:11 +0200, Axel Braun wrote:
> I asked: I have already POs with my supplier and incoming goods at a later 
> time than I request (late supplier move)?
> 
> you wrote:You are just not thinking with the time dimension in mind. There is 
> not just 1 purchase involved.
> 
> This exactly what I asked. I can not know if my goods are late unless I have 
> received some kind of confirmation back from supplier.

Or he is late. Such information comes with simply the time going, that's
what I call "thinking with the time dimension".

> To receive a 
> confirmation, I have to issue a Purchase order.

We are talking about things going wrong, not things following workflow.

> But maybe we have a misunderstanding in wording: A purchase request is a 
> request to purchase goods. It may be linked to some authorisation and 
> approval 
> workflows. 

Yes.

> In case a purchase request is confirmed, it is linked to a vendor (sourcing) 
> and transformed into a purchase order. Now this PO can have a later delivery 
> date than what I requested, which affects my ability to deliver in time to 
> the 
> customer -> I need to reschedule my sale to the customer.

This is not managed by Tryton. It is impossible to do because there is
no link between a purchase and a sale.

-- 
Cédric Krier

B2CK SPRL
Rue de Rotterdam, 4
4000 Liège
Belgium
Tel: +32 472 54 46 59
Email/Jabber: [email protected]
Website: http://www.b2ck.com/

Attachment: pgpz8ptrxYBr3.pgp
Description: PGP signature

Reply via email to